Removing and installing refrigerant shut-off valve 5
N643
Special tools and workshop equipment required
Torque wrench
V.A.G 1410/
Vehicle diagnostic tester
Air conditioner service station
Removing
Observe safety precautions (see “Safety precautions when working on air conditioning systems”).
Observe safety precautions when working in the vicinity of high-voltage components (see “Safety precautions when working in the vicinity of high-voltage components”).
Comply with notes (see “Working on refrigerant circuit”).
Observe the risk rating of the high-voltage system (repair group 00: Risk category of the high-voltage system).
Using
Vehicle diagnostic tester
, initiate basic setting, then perform function "Charge refrigerant circuit".
Note
Always perform the basic setting
“Charge refrigerant circuit” using the
Vehicle diagnostic tester
, to make sure that all valves of the refrigerant circuit are opened. This is the only way to extract the complete refrigerant from the circuit.
The
Vehicle diagnostic tester must not be disconnected from the vehicle during the entire extraction, evacuation and charging process.
To prevent the intrusion of moisture, all components of the refrigerant circuit which have been opened must be sealed with suitable plugs.
Extract refrigerant with air conditioning service station
. Comply with notes (see the separate procedure).
Remove lower wheel housing liner at front right (repair group 66: Wheel housing liner; Removing and installing front wheel housing liner).
CAUTION
Risk of freezing injury caused by escaping pressurised refrigerant.
There is a risk of injury to the skin and parts of the body due to freezing.
Always wear safety gloves.
Always wear safety goggles.
Extract refrigerant, and open the refrigerant circuit immediately afterwards.
If more than 10 minutes passed since the refrigerant has been extracted, do not open the refrigerant circuit prior to extracting refrigerant anew. Due to re-evaporation, pressure will be built up in the refrigerant circuit.
Unscrew bolts (2) and (6).
Disconnect refrigerant lines (1) and (3) from refrigerant shut-off valve 5
N643 (5).
Separate connector (7).
Unscrew bolts (4).
Remove
refrigerant shut-off valve 5
N643 (5).
Installing
Installation is carried out in the reverse order. When installing, note the following:
Renew seals (see the separate procedure).
Moisten with refrigerant oil to ease installation of refrigerant lines.
If the valve has been renewed, it must be programmed using
Vehicle diagnostic tester.
Using
Vehicle diagnostic tester
, initiate basic setting, then perform function "Charge refrigerant circuit".
Note
Always perform the basic setting
“Charge refrigerant circuit” using the
Vehicle diagnostic tester
, to make sure that all valves of the refrigerant circuit are opened. This is the only way to charge the complete circuit.
The
Vehicle diagnostic tester must not be disconnected from the vehicle during the entire extraction, evacuation and charging process.
If the component has been renewed due to a mechanical defect (e.g. wear), purge the refrigerant circuit.
Only start engine after refrigerant circuit has been assembled.
Only start engine when refrigerant circuits are charged.
Specified torques (see “System overview – refrigerant circuit, e-Golf with heat pump”)
Install wheel housing liner (repair group 66: Wheel housing liner; Removing and installing front wheel housing liner).
TorqFix answers live for your specific car — tell it the engine code to check the available procedures, torque figures and wiring for that variant.
Ask about my car →Other VW procedures
- Heat exchanger for high-voltage battery VX63 with refrigerant shut-off valve for high-voltage battery heat exchanger N542
- Heat exchanger for high-voltage batteryVX63 with refrigerant shut-off valve for high-voltage battery heat exchanger N542
- Removing and installing refrigerant line between condenser, refrigerant shut-off valve 5N643 and refrigerant shut-off valve 1N696
- Removing and installing refrigerant line between reservoir, refrigerant shut-off valve 5N643 and valve unit of heat pump
- Removing and installing refrigerant shut-off valve 1 N696
- Removing and installing refrigerant shut-off valve 1N696
- Removing engine
- Removing and installing camshaft – VW Golf Cabriolet
- Adjusting valve timing – VW Passat B5
- Removing and installing camshafts – VW Passat B6
Who makes these pages, and how
TorqFix was built by a mechanic — after a 2,700 km drive with five roadside repairs that no diagnostic tool could explain.
Workshop figures are drawn from the available source documentation. Pages are assembled automatically, with source instructions and explanatory material presented together. Some explanations use AI assistance. Automated source checks are not a claim that a mechanic reviewed every page; read the source conditions and the editorial method below.
Variants of the same model differ. Cross-check torque against the factory manual for your engine before final tightening.
Seen a figure that does not match your manual? Write to us — we correct it and note when. support@torqfix.com
The story behind TorqFix → · How these pages are made →Workshop data on this page last updated 20 Sep 2026.