🧭 Before you start
Fits: Audi A4 Cabriolet B6/B7 (8H), Audi A4 B6/B7 (8E)
- Renewed: bolts as follows
Don't miss
- The bottom bolt (right arrow) does not have to be completely removed.
- If the following appears on the display, an incorrect software version has been loaded:1. >TEST2. LEARNIf this is the case, download the correct software version from the "„Audi ServiceNet“" under "„Workshop Equipment“".
- If the display indicates "„[OK
- The stop plateVAS 6395/3 must not be loosened until the work sequence has been completed. — To continue, press v button (item 4).
- If the display indicates "„FAULT [OK
🔩 Torque settings
Values can differ between engine variants — check the code stamped on your block.
| Torque | Fastener / step |
|---|---|
| 10 Nm (7.4 lb-ft) | Tighten bolts (1, 2, 3) |
| 5 Nm (3.7 lb-ft) | Tighten bolts (1, 2, 3) |
| 8 Nm (5.9 lb-ft) | Secure stop plateVAS 6395/3 with bolts for heat shield |
ℹ️ Always cross-check the exact figure against your vehicle's factory manual before final tightening — a wrong torque can damage the engine. These values are extracted from workshop data and may not cover every variant or revision.
📐 20 workshop diagrams for ASB
Real factory drawings for this job — timing marks, bolt locations and routing. Locked in the free view.
📋 Procedure
- Carefully pull engine cover panel off four retaining pins one after the other (arrows).
- Remove bolts (arrows) and detach heat shield for turbocharger. [Note: The bottom bolt (right arrow) does not have to be completely removed.]
- Connect testerVAS 6395/1 with connecting wireVAS 6395/2 to positive battery terminal (arrow) and negative battery terminal. [Note: If the following appears on the display, an incorrect software version has been loaded:1. >TEST2. LEARNIf this is the case, download the correct software version from the "„Audi ServiceNet“" under "„Workshop Equipment“".]
- ⚠ Risk of damage to turbocharger 1 control unit J724.Before continuing, check whether the correct software version is loaded in the testerVAS 6395/1. To do so, proceed as follows: — Unplug electrical connector for turbocharger 1 control unit J724.
- Connect connection leadVAS 6395/2 to turbocharger 1 control unit J724 and to testerVAS 6395/1.
- To continue, press v button (item 4). [Note: If the display indicates "„[OK]“", the adjustment range of the turbocharger 1 control unit J724 is stored.If the display shows "„FAULT [OK]“", tap gently several times on the housing of turbocharger 1 control unit J724 with the handle of a screwdriver and repeat the check by pressing v button (item 4).]
- Unclip retaining clip (1) and move electrical wire clear.
- Secure stop plateVAS 6395/3 with bolts for heat shield. Tightening torque: 8 Nm. — 8 Nm (5.9 lb-ft)
- ⚠ The stop plateVAS 6395/3 must not be loosened until the work sequence has been completed. — To continue, press v button (item 4).
- While the voltage value is being determined, keep tapping gently on the housing of turbocharger 1 control unit J724 until the display indicates the following:
- Note voltage value. [Note: If the display indicates "„FAULT [OK]“" or the voltage is less than 3.3 V or greater than 3.7 V, unplug testerVAS 6395/1 and repeat the complete procedure .]
- By pressing buttons ↑(item 5) and ↓(item 6), adjust turbocharger 1 control unit J724 so that coupling rod can be accessed easily for removal.
- Unclip circlips (arrows) and dispose of them, detach coupling rod.
- By pressing buttons ↑(item 5) and ↓(item 6), adjust turbocharger 1 control unit J724 so that bolts for J724 can be accessed easily.
- Disconnect connection leadVAS 6395/2 from turbocharger 1 control unit J724.
- ⚠ Power supply for testerVAS 6395/1 must remain connected. — Remove bolts (1, 2, 3) and dispose of them.
- Remove old turbocharger 1 control unit J724 and dispose of it.
- ⚠ Check that the three insulating washers are fitted between turbocharger 1 control unit J724 and the bracket. — Install new turbocharger 1 control unit J724 in reverse sequence of removal.
- Fit new bolts as follows:
- Initially hand-tighten bolts.
- Connect connection leadVAS 6395/2 to new turbocharger 1 control unit J724.
- To continue, press v button (item 4).
- Select menu item "„NEXT“" with ↓ button (item 6).
- To continue, press v button (item 4). [Note: If the display indicates "„CHECK“", the adjustment range of the new turbocharger 1 control unit J724 must be checked .If the display indicates "„FAULT“", the new turbocharger 1 control unit J724 must be renewed for a second time.]
- To continue, press v button (item 4).
- To continue, press v button (item 4).
- Insert coupling rod.
- Fit circlips (arrows).
- Press turbocharger 1 control unit J724 towards the rear without applying force (arrow) until lever (1) rests lightly on stop plateVAS 6395/3.
- Hold J724 in this position.
- Tighten bolts (1, 2, 3) to 5 Nm. — 5 Nm (3.7 lb-ft)
- To continue, press v button (item 4). [Note: If [OK] is indicated on display, terminate adjustment .If "„CHECK“" is indicated on display, proceed as follows.]
- Loosen bolts (1, 2, 3) until turbocharger 1 control unit J724 can just be moved by applying light force in the direction stated:
- Tighten bolts (1, 2, 3) to 5 Nm. — 5 Nm (3.7 lb-ft)
- To continue, press v button (item 4).
- Tighten bolts (1, 2, 3) to 10 Nm. — 10 Nm (7.4 lb-ft)
- To continue, press v button (item 4).
- Remove stop plateVAS 6395/3.
- Secure electrical wiring with retaining clip (1).
- To continue, press v button (item 4). [Note: If the display indicates "„FAULT“", the new turbocharger 1 control unit J724 must be renewed .]
- Unplug electrical connectors for testerVAS 6395/1.
Ask TorqFix about your Audi ASB — it answers with the exact sequence for that engine and the workshop drawing for each step. First question is free after a 20-second sign-up, no card.
Ask about your Audi ASB — free → or sign up free to see the drawingsOther AUDI procedures
- Removing and installing air filter element – Audi
- Removing cylinder head - vehicles from 09.2005 onwards – Audi
- Removing and installing mechanical exhaust gas recirculation valve
- Checking fuel pressure regulating valve N276
- Cylinder head cover - exploded view · 1 torque figures
- Removing and installing toothed belt – Audi · 56 torque figures
- Removing engine – Audi A8 D3 · 41 torque figures
- Removing camshaft timing chain from camshafts – Audi A6/A7 C7 · 38 torque figures
- Installing engine – Audi A8 D4 · 36 torque figures
- Removing and installing camshaft timing chain · 29 torque figures
Who makes these pages, and how
TorqFix was built by a mechanic — after a 2,700 km drive with five roadside repairs that no diagnostic tool could explain.
The figures on this page come from manufacturer workshop documentation and are shown as they are. The page is assembled automatically from that data — it is not written by an AI. The AI works in the chat, where it answers for your specific car. It writes nothing here.
Variants of the same model differ. Cross-check torque against the factory manual for your engine before final tightening.
Seen a figure that does not match your manual? Write to us — we correct it and note when. support@torqfix.com
The story behind TorqFix →Workshop data on this page last updated 20 Sep 2026.