Models recorded for this source: Audi A8 D3 (4E, 2002–2010)

  • Special tools named: puller

Don't miss

  • The residual pressure valve (2) MUST NOT be loosened or removed.
  • Wheel bearing housing must be supported to avoid damaging joints of upper links.
  • Use felt-tip pen to mark position of subframe on body.
  • Spacers (arrow B) are fitted between subframe and front gearbox mounting to allow stress-free alignment. The gap between the subframe and front gearbox mounting must be re-set accordingly on installation.
  • Lower subframe approx. 80 mm at the rear (subframe mounting must be beneath longitudinal member).

📋 Procedure

  1. Position vehicle on lifting platform (see the separate procedure).
  2. Set up engine support bracket and take up weight of engine (repair group 13).
  3. Remove wheel trim; on light-alloy wheels, pull off trim cap (use puller in vehicle tool kit).
  4. Remove wheels.
  5. Secure brake discs with one wheel bolt each.
  6. Clean area around air connection.
  7. Unscrew connection pieces (1) on both sides at residual pressure valves (2). This will allow air to escape. [Note: The residual pressure valve (2) MUST NOT be loosened or removed.]
  1. Seal both connections. Take care to prevent dirt entering the connections.
  2. Vehicles with auxiliary heater: Unscrew bolts (arrows) from exhaust pipe at noise insulation.
  3. Release quick-release fasteners (1) to (4) and remove noise insulation panels.
  4. Remove cross piece for noise insulation at subframe (arrows).
  5. Unbolt coupling rod of vehicle level sender (1) from track control link on both sides.
  6. Unplug connector from vehicle level sender on both sides.
  7. Remove coupling rod (2) on both sides (see the separate procedure).
  8. Unscrew nuts from both guide links and track control links at subframe. [Note: Wheel bearing housing must be supported to avoid damaging joints of upper links.]
  1. Lift both wheel bearing housings approx. 50 mm clear and tie in place. To do so, guide tensioning strap T10038 through hole in body.
  1. Remove bolts (2) and detach bracket (1) for charge air cooler.
  2. Remove bolts (2) and (3) detach bracket (1) for charge air cooler.
  3. Remove bolt (arrow) for air pipe on left and right.
  1. Use felt-tip pen to mark position of subframe on body.
  2. Position engine and gearbox jack V.A.G 1383 A with suitable wooden block under subframe and press subframe upwards lightly.
  3. Remove bolts (1) for engine mounting.
  4. Remove bolts (2) and (3) and detach engine cross member (4) with anti-roll bar.
  5. Remove bolts (5) and (6).
  6. Slacken nut (arrow) for front gearbox mounting.
  7. Remove bolts for front gearbox mounting (arrows A) on left and right. [Note: Spacers (arrow B) are fitted between subframe and front gearbox mounting to allow stress-free alignment. The gap between the subframe and front gearbox mounting must be re-set accordingly on installation.]
  1. Position engine and gearbox jack V.A.G 1383 A beneath subframe and press subframe up lightly.
  1. Lower subframe approx. 80 mm at the rear (subframe mounting must be beneath longitudinal member).
  2. Remove spacers between subframe and front gearbox mounting.
  3. Remove bolt from left guide link.
  4. Turn steering wheel to right.
  5. Press subframe to right as far as possible and pull left guide link out of subframe. [Note: Detached guide links must not be subjected to load, as this would damage guide link joints.]
  1. Remove right guide link from subframe in the same way as left link.
  2. Pull bolts out of track control link on right and left.
  3. Slide subframe as far as possible to right or left and swivel out left/right track control link.
  4. Lower subframe.
  1. Initially only hand-tighten bolts/nuts for components with bonded rubber bush. Wheel bearing housing must first be raised (to reference position) before tightening bolts/nuts (see the separate procedure).
  2. Insert track control links and guide links in subframe.
  3. Position subframe at marked location with respect to body.
  4. Fit spacers (arrow B) between subframe and front gearbox mounting (repair group 37).
  5. Loosely screw all bolts into engine cross member and subframe by hand. [Note: When fitting engine cross member, make sure centring element of engine mountings is located in mounting holes in engine cross member.]
  1. Use 8 mm drift (A) to align engine cross member with subframe. Holes in subframe (1) and engine cross member (2) must be vertically aligned.
  2. Ensure subframe is stress-free when installed (repair group 37).
  3. To permit stress-free alignment of subframe, tighten nut for front gearbox mounting (arrow) on left and right sides after wheel alignment has been checked and adjusted (repair group 37).
  4. Install spacers (repair group 37).
  5. Tighten subframe bolts to torque setting, but do not turn further (only tighten bolts to final setting after wheel alignment has been checked and adjusted).
  1. ⚠ All bolts and nuts must be fully tightened according to specifications before the vehicle is driven on public roads. — Position engine and gearbox jack V.A.G 1383 A with suitable wooden block under subframe and press subframe upwards lightly.
  2. Tighten bolts (1) for engine mounting (repair group 10).
  3. Fit engine cross member (4) with anti-roll bar in position and tighten bolts (2)10.
  4. Diagonally tighten bolts (3) and (5) to torque setting only. Bolt (5), bolt (3)
  5. Tighten bolts (6).
  6. Insert bolts for track control links on right and left and tighten bolts (see the separate procedure).
  7. Insert bolts for guide links on right and left and tighten bolts (see the separate procedure).
  8. Attach cross piece for noise insulation at subframe (arrows).
  1. Screw in bolt (arrow) for air pipe on left and right (repair group 13).
  2. Fit bracket (1) and screw in bolts (2)13.
  3. Fit bracket (1) and screw in bolts (2) and (3)13.
  1. Screw coupling rod of vehicle level sender (1) onto track control link (see the separate procedure).
  2. Plug in connector of vehicle level sender on right and left.
  3. Attach coupling rod (2) on right and left and (see the separate procedure).
  4. Screw bolt (3) for air spring strut onto track control link (see the separate procedure).
  5. Screw on connection piece (1) at residual pressure valve (2).
  6. Fit noise insulation (repair group 50).
  7. Fit and secure wheels Wheels and tyres44.
  8. Set down vehicle on its wheels (see the separate procedure).
  9. Check and adjust wheel alignment (see the separate procedure).
  10. Following wheel alignment, tighten subframe bolts to final setting by turning through specified angle.
  11. Re-adapt reference position (see the separate procedure).

Who makes these pages, and how

TorqFix was built by a mechanic — after a 2,700 km drive with five roadside repairs that no diagnostic tool could explain.

Workshop figures are drawn from the available source documentation. Pages are assembled automatically, with source instructions and explanatory material presented together. Some explanations use AI assistance. Automated source checks are not a claim that a mechanic reviewed every page; read the source conditions and the editorial method below.

Variants of the same model differ. Cross-check torque against the factory manual for your engine before final tightening.

Seen a figure that does not match your manual? Write to us — we correct it and note when. support@torqfix.com

The story behind TorqFix → · How these pages are made →

Workshop data on this page last updated 20 Sep 2026.